At last, in September 2006, things started to happen! We'd chosen our design
almost a year previously, but planning permission took a while and both bushfire
and environmental issues had to be dealt with.
|
|
|
|
Ground zero - trenches and reinforcement for the footings (6th September).
|
The concrete has been poured, and the bricklayers start work (19th September).
|
Bricklaying finished - the perimeter walls (22nd September).
|
|
|
|
|
Next come the pillars, bearers and joists for the floor (5th October)
|
And the floor itself (15th October).
|
And, in one day, the wall frames go up in rough assembly (20th October).
|
|
|
|
|
The hole for the sewerage treatment got an unintended visit from the builder's dog.
|
But now the Biolytix system is installed - no more heffalump trap! (28th October) |
The roof trusses are up, everything is bolted together and the verandah is under way (November 10th).
|
|
|
|
|
Half a roof is better than none!
|
The view from what will be the living-room window |
December 8th, and the cladding is nearly done
|
|
|
|
|
Finally, the New Year sees us at lockup stage
|
Next thing we need an even bigger hole ... |
... for our underground 105,000 litre water tank
|